New Court Development

The redevelopment of Row one is now well underway. The council has started lifting the grass and recycling it around various Council venues. This week the contract was signed and work will begin in the next few days. Weather permitting the initial stage will take 6 - 8 weeks. The asphalt will then be left to set for 4 weeks. After the four week period, the top layers of rebound Ace will be laid.

Along with the hard work of the committee, we would like to acknowledge the work that Chris Glasson and Lindsay North have put in to make this project a reality.